Lakeway to Marble Falls Transmission Line Storm Hardening Project

LCRA Transmission Services Corporation is performing storm hardening on the 23-mile Lakeway-Marble Falls transmission line and other area transmission lines within the corridor.

The project will increase the reliability and safety of the structures and conductor by ensuring the transmission lines meet or exceed current National Electrical Safety Code and LCRA TSC design standards.

Latest Update – September 2024

Construction and cleanup are complete on the segment of transmission line between Bee Creek and Paleface substations in Travis County. Crews have started work on the section between the Paleface and Marble Falls substations. Work on that portion is expected to be complete by mid-April 2025. Following that, crews will move to the section between Lakeway and Bee Creek substations to replace a conductor and final structures near Lakeway Airpark. This work will require crews to access each structure between Lakeway and Bee Creek substations. Overall project cleanup is scheduled for late June 2025.

Previous Project Updates

April 2024

Crews are performing construction work on transmission line segments from near the intersection of RM 620 and Stewart Road in Lakeway to west of SH 2322 and the Pedernales River in Spicewood. The construction work in the area is scheduled to be completed in late June.

September 2023

View the hauling routes being used for the project with this map.

Related vehicle activity will be concentrated on the east end of the project, going from Lakeway to Bee Creek, early September through November.

July 2023
Construction begins in July on the east end of the project. LCRA staff members and contractors will be present along the rights of way, and crews using large vehicles and equipment will be present during construction.

Program Timeline

Summer 2023
Construction activity begins on the eastern portion of project, Lakeway-Paleface, in Travis County. Clearing and excavation will continue into the Paleface-Marble Falls section, crossing into Burnet County, when east section is complete.
September 2023-May 2024
Replacement of structures and conductor planned for Lakeway-Paleface section.
Summer 2024
Right-of-way cleanup planned for Lakeway-Paleface section. Remaining excavation and clearing to be performed on the western portion of project, Paleface-Marble Falls.
September 2024 – May 2025
Structures and conductor to be replaced on western portion of project, Paleface-Marble Falls.
Summer 2025
ROW cleanup planned in Paleface-Marble Falls section.

Contact

Please submit any questions using the Contact LCRA form.